Golden Mussel Mitigation Project Electrical Install at Check 22

Kettleman City, California

Document Stage

Post-Decision

Description

The field division plans to install a 120v receptacle and lighting for the chemical injection system for the Golden Mussel Mitigation Project. This work will involve excavating a 2-feet wide by 2-feet deep by 1,180-feet long trench. The trench will start at Check Site 22 of the State Water Project and run along the secondary aqueduct access road. The trench will terminate at the start of the Coastal Branch. A backhoe will be used to dig the trench. Once PVC conduit is installed, the trench will...