Description

The ITP authorizes the construction, operation, and maintenance of a 23 mile long double-circuit 220 kilovolt kV transmission line looping the existing Big Creek 3-Springville transmission line to the existing Rector substation, creating the new Big Creek 3-Rector and Rector-Springville transmission line circuits. Construction was to result in impacts to 98.30 acres of California tiger salamander Ambystoma californiense habitat including temporary impacts to 52.62 acres and the permanent loss of...